Skip Ribbon Commands
Skip to main content

Case Study

MMC Ltd - London

UK Data Centres case studies 2013 - MMC MAIN.jpg

Challenge

To identify and acquire mirror Data Centre site more than 50km from the primary site to comply with Financial Regulations and support EMEA network. It was deemed uneconomic to upgrade the existing infrastructure.
 

Solution

  • Working in collaboration with Corporate Solutions, we reviewed the available opportunities and provided a report on shortlisted options.
  • Agreed technical requirements in respect of power/cooling loads.
  • Completed due diligence on selected site and agreed legal documentation.
  • Provided project management services to monitor the landlord's upgrade works.
 
Results
  • Acquired existing 20,000 sqft Data Centre.
  • Terms agreed in line with recommendations.
  • Migration complete prior to lease expiry at existing site.
 
Michael Pullen, Marsh & McLennan commented:
 
“Data Centre transactions are never quick or simple, but Jones Lang LaSalle really worked hard to pull all the parties together, and persevered throughout the transaction to make sure that everybody met the time parameters agreed, to bring this through to a very successful conclusion for all concerned.”
 

All Case Studies

 

 

King’s Cross Central - Joint venture advice and land value realisation/emea/en-gb/case-studies/100/king-s-cross-central-joint-venture-advice-and-land-value-realisationKing’s Cross Central - Joint venture advice and land value realisation
Valuation of ProLogis portfolio in Poland/emea/en-gb/case-studies/101/valuation-of-prologis-portfolio-in-polandValuation of ProLogis portfolio in Poland
Project management for ABN AMRO, Warsaw/emea/en-gb/case-studies/102/project-management-for-abn-amro-warsawProject management for ABN AMRO, Warsaw